Window Schedule: How to Read One and Take Off Every Window

A window schedule is the table in a plan set that lists every window type with its size, rough opening, operation, glazing and other data, keyed to tags on the floor plans and elevations. To read it, match the tag to a row and read across. For a takeoff, it gives you window counts by type, wall area to deduct, and the linear feet of trim, sill and flashing tape around each opening.
Measure Plans in Minutes
Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.
A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.
What is a window schedule?
It is the window part of the drawings written as a table. The plans and elevations show where each window goes. The schedule says what it is, how big the hole in the framing must be, and how it performs.
It usually sits in the architectural set near the door schedule. Reading it is one piece of how to read blueprints for construction, and the door side is covered in how to read a door schedule.
How are windows tagged on the plans?
Each window on the floor plan has a tag, often a letter or number inside a small shape by the opening. The same tag appears on the exterior elevations. On many sets one row covers a window type, so ten identical windows all carry the tag A and the schedule gives a quantity.
Other sets give each opening its own mark. Either way, the tag count on the plans should match the schedule quantity. When it does not, the schedule and the drawings disagree, and that is an RFI.
What columns are on a typical window schedule?
Layouts vary by office, and each project's schedule and legend win over this list. These are the columns you will run into most:
| Column | What it tells you |
|---|---|
| Mark or type | The tag that matches the plan and elevations |
| Unit size | The outside frame size of the window, width x height |
| Rough opening (RO) | The framed hole the window goes into, a little larger than the unit |
| Operation | Double hung, casement, awning, fixed, slider and so on |
| Glazing | Insulated glass, low-E coating, tempered or laminated glass |
| U-factor and SHGC | NFRC energy ratings, when the designer lists them |
| Head height | Finished floor to the top of the window, which tells the framer where the header goes |
| Quantity | How many of that type, on schedules organized by type |
| Remarks | Egress, tempered locations, mulled units, hardware, finish |
Window schedule example
Here is a sample window schedule for a small house, made up to show the format. The energy values are placeholders, not ratings for any real product.
| Type | Operation | Unit size (W x H) | Rough opening | Glazing | U-factor | SHGC | Head ht | Qty | Remarks |
|---|---|---|---|---|---|---|---|---|---|
| A | DH | 35-1/2" x 59-1/2" | 36" x 60" | IG, low-E | 0.30 | 0.25 | 6'-8" | 6 | |
| B | CSMT | 23-1/2" x 47-1/2" | 24" x 48" | IG, low-E | 0.29 | 0.27 | 6'-8" | 4 | Hinge per elevation |
| C | FX | 47-1/2" x 47-1/2" | 48" x 48" | IG, low-E | 0.27 | 0.30 | 6'-8" | 2 | |
| D | AWN | 35-1/2" x 23-1/2" | 36" x 24" | IG, low-E, tempered | 0.30 | 0.27 | 6'-8" | 3 | Over tub |
Read type A across: a double hung window with a 35-1/2 by 59-1/2 inch frame, set in a 36 by 60 inch rough opening, insulated low-E glass, head at 6'-8" above the floor, six of them on the job.
Rough opening vs unit size
The unit size is the window. The rough opening is the hole in the framing, left a little larger so the installer can shim, level and seal it. Pella's 250 Series architectural design manual gives the rule as rough opening = frame dimension + 1/2 inch, in both width and height, for typical installations. Pella also says the need for extra clearance should be reviewed for large units and masonry construction.
That 1/2 inch splits into 1/4 inch on each side. Other makers and product lines publish their own numbers, so the framer works from the manufacturer's chart for the window actually bought. If the schedule shows only one size, check whether it is labeled as unit or RO before you frame or deduct anything.
Window schedule abbreviations
The operation column is mostly codes. These are common ones, but each office has its own list and the abbreviation sheet in the set decides:
| Code | Usually means |
|---|---|
| DH | Double hung |
| CSMT | Casement |
| AWN | Awning |
| FX | Fixed |
| RO | Rough opening |
| MO | Masonry opening |
| GL | Glass or glazing |
| TYP | Typical |
Watch the short ones. SH can mean single hung on a window schedule, but archisoup's architectural abbreviations list gives SH as shelf or shelving. The rest of the shorthand on a set is covered in construction abbreviations on blueprints.
What do U-factor and SHGC mean on a window schedule?
Both come from the National Fenestration Rating Council (NFRC) label. U-factor measures how well a product keeps heat from escaping, and lower is better. NFRC gives a range of 0.20 to 1.20 for windows.
SHGC (solar heat gain coefficient) runs from 0 to 1. Low numbers resist solar heat and high numbers let it in. For a takeoff these columns matter at purchase: the window you price has to meet the numbers on the schedule.
Window type elevations
Many sets draw each window type as a small elevation next to the schedule. It shows the operation, mullions, grilles and any mulled units. A mulled pair under one tag is two units in one opening, which changes both the count and the rough opening.
The building elevations show where each type lands on each face. Head heights, sills and trim profiles are easiest to check there (see how to read elevation drawings).
How do you do a window takeoff from the schedule?
- Count tags by type on every floor plan and check them against the schedule quantities.
- Write one takeoff line per window type with its count.
- Work out the rough opening area per type and total the wall deduction.
- Measure trim, sill and flashing tape from the rough opening perimeter.
- Note glazing, energy values and remarks that change price, such as tempered glass.
Worked example: counts and wall area deductions
Using the sample schedule and the rough opening sizes, converted to feet:
| Type | Qty | RO (ft) | Area each | Area total | RO perimeter each | Perimeter total |
|---|---|---|---|---|---|---|
| A | 6 | 3 x 5 | 15 SF | 90 SF | 16 LF | 96 LF |
| B | 4 | 2 x 4 | 8 SF | 32 SF | 12 LF | 48 LF |
| C | 2 | 4 x 4 | 16 SF | 32 SF | 16 LF | 32 LF |
| D | 3 | 3 x 2 | 6 SF | 18 SF | 10 LF | 30 LF |
| Total | 15 | 172 SF | 206 LF |
Say the exterior walls measure 160 LF around and 9 feet tall. Gross wall area is 160 x 9 = 1,440 SF. Less 172 SF of windows, the net is 1,268 SF before doors come out. A wall square footage calculator does the same subtraction one wall at a time.
Worked example: trim, sill and flashing tape
Each rough opening perimeter is 2 x (width + height). For type A that is 2 x (3 + 5) = 16 LF, and 206 LF for all fifteen windows.
- Casing on four sides (picture frame): about 206 LF before miter allowance and waste.
- If the detail shows a stool and apron instead of a bottom casing, move the bottom piece to a sill line. The sill run is the total of the widths: (3 x 6) + (2 x 4) + (4 x 2) + (3 x 3) = 43 LF, which leaves 206 less 43 = 163 LF of casing.
- Flashing tape around the full opening: 206 LF plus whatever lap the manufacturer's instructions or the flashing detail call for. Some details tape only the jambs and head, which would be 206 less 43 = 163 LF.
Write the method in the notes column so whoever checks the takeoff knows which version you carried. Interior finishes around the windows, such as paint and stool material, connect to the room finish schedule.
Counting windows on the PDF
In MeasureFloorPlan's Takeoff mode, the Count tool (shortcut C) adds one click per item. Use the Windows category, or Other with a custom name per type, such as "Window A DH". Counts land in the takeoff table and the CSV, Copy table and PDF exports. Distance runs can be grouped into named line items with subtotals, which works for casing and flashing tape.
Measure Plans in Minutes
Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.
A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.
Frequently Asked Questions
What is a window schedule on a set of plans?
It is a table that describes each window type or mark in the project: size, rough opening, operation, glazing, energy values, head height and remarks. The tag next to each window on the floor plan tells you which row applies.
What is the difference between rough opening and window size?
The unit (frame) size is the outside of the window itself. The rough opening is the framed hole it goes into, which is slightly larger. Pella, for example, sets the rough opening at the frame size plus 1/2 inch in width and height for typical installs.
What do DH, CSMT and AWN mean on a window schedule?
DH is double hung, CSMT is casement and AWN is awning. You will also see FX for fixed. Offices use different codes, so the abbreviation list on the plan set decides what each one means on that job.
What do U-factor and SHGC mean on a window schedule?
They are NFRC ratings. U-factor measures how well the window keeps heat from escaping, and lower is better. SHGC, on a 0 to 1 scale, measures how much solar heat gets through. Low numbers resist solar heat.
Should wall area deductions use the rough opening or the window size?
Either works if you use it every time and write it in your notes. The rough opening is the hole in the wall, so it is the more natural choice for siding, sheathing and drywall. The difference per window is small.