MeasureFloorPlan

Home › Learn › Door Schedule: How to Read One and Take Off Every Opening

Part of: What Is a Takeoff in Construction? How to Do One From Plans

Door Schedule: How to Read One and Take Off Every Opening

Door Schedule: How to Read One and Take Off Every Opening

A door schedule is the table in a plan set that describes every door opening, one row per door mark. To read it, find the tag on the floor plan, look up that mark in the schedule, and read across: size, door type, material, frame, fire rating, hardware set and remarks. For an estimator, those rows become counts by size and type, frame counts, hardware sets and trim footage.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

What is a door schedule?

It is the door section of the drawings written as a table instead of notes. The floor plan shows where each door sits and which way it swings. The schedule says what the door actually is.

It sits in the architectural set, often on the same sheet as the window schedule, and is part of a larger skill covered in how to read blueprints for construction. The plan symbols themselves (swing arcs, wall openings) are covered in how to read a floor plan.

How do door tags on the plan link to the schedule?

Each door on the floor plan carries a tag, usually a number in a small circle, hexagon or box next to the swing. That number is the door mark, and it matches one row in the schedule. A common scheme numbers doors after the room they open into, so the doors into room 101 become 101, 101A and 101B.

Allegion, the hardware maker, warns not to mix up door number and door type. The number is unique to one opening. The type is a design, such as half glass or narrow lite, and many openings can share it.

What columns are on a typical door schedule?

There is no single required layout, and each project's schedule and legend win over anything here. The list below follows the columns Allegion recommends in its article Building a Better Door Schedule.

ColumnWhat it tells you
Mark (door number)The unique ID that matches the tag on the plan
Size (W x H x thickness)Opening width, height and door thickness. Allegion gives 1-3/4" as the typical commercial thickness
Single or pairWhether a 6'-0" opening is one wide door or two 3'-0" leaves
Door typeA letter that points to a door type elevation (flush, half glass, narrow lite)
Door materialHM, WD, AL, glass and so on
Frame type and materialA letter and number that points to a frame elevation, plus HM, WD or AL
DetailsHead, jamb and sill detail references
Fire ratingMinutes, such as 20, 45, 60 or 90. Blank, 0 or NON for unrated
Hardware setThe number of the hardware group in the specs
RemarksAnything else: closers, access control, glazing, undercuts, finish

Door schedule example

Here is a sample door schedule for a small office suite, made up to show the format. It is not from a real project.

Sample door schedule (illustration only)
MarkLocationSize (W x H x T)Door typeDoor matlFrame typeFrame matlFire rating (min)HW setRemarks
101Corridor to Office 1013'-0" x 7'-0" x 1-3/4"AWD-SCF1HM203
102Corridor to Office 1023'-0" x 7'-0" x 1-3/4"AWD-SCF1HM203
103Corridor to Storage3'-0" x 7'-0" x 1-3/4"BHMF1HM455Field paint
104Corridor to Restroom3'-0" x 7'-0" x 1-3/4"AWD-SCF1HM7Privacy lock
105Corridor to ConferencePR 3'-0" x 7'-0" x 1-3/4"CWD-SCF2HM4Pair, 6'-0" opening
106Lobby to Exterior3'-0" x 7'-0" x 1-3/4"DALF3AL1Storefront

Read door 103 across the row: a 3 foot by 7 foot hollow metal door, 1-3/4 inches thick, type B, in a hollow metal frame of type F1, rated 45 minutes, hardware set 5, field painted. Door 105 is a pair, so one row means two leaves.

What does a door size like 3070 mean?

Door sizes are often written as four digits: feet and inches of width, then feet and inches of height. Andersen gives 3068 as its example, a door 3 feet 0 inches (36 inches) wide by 6 feet 8 inches (80 inches) tall. Read the same way, 3070 is 3'-0" x 7'-0" and 2868 is 2'-8" x 6'-8".

Commercial schedules more often spell the size out, as in the sample above. Either way, check whether a wide number means one door or a pair. Allegion's example is a 4'-0" opening, which could be a single wide door or two 2'-0" leaves.

Door schedule abbreviations

Allegion lists these as the common door materials: HM (hollow metal), WD (wood), AL (aluminum), FRP (fiberglass reinforced polymer), GL (glass), SS (stainless steel), EX (existing) and LPWD (laminated plastic wood door). On wood doors you will also see SC for solid core and HC for hollow core, often joined as WD-SC.

Abbreviations are not fully standard between offices, so the abbreviation list on the cover or general sheet decides. The wider set of shorthand is in construction abbreviations on blueprints.

Door type and frame type elevations

The door type and frame type columns hold only a letter or code. The drawings for those codes are small elevations, usually printed next to the schedule: type A might be a flush door, type B a door with a narrow vision lite, F1 a single frame, F2 a frame for a pair.

Look at them before you price. A type with a glass lite adds glazing, and a frame type with a sidelight or transom is a bigger frame than the door size suggests. Allegion also notes that hardware choices can depend on stile and rail sizes shown in these elevations. Exterior frames show up again on the building elevations (see how to read elevation drawings).

How do fire ratings show up on a door schedule?

Allegion recommends fire ratings in minutes (20, 45, 60, 90, 180), with unrated openings shown as 0, NON or left blank. The Steel Door Institute says doors are typically rated at three fourths of the wall rating, so a 1 hour wall usually gets a 3/4 hour (45 minute) door and a 2 hour wall a 1-1/2 hour door.

SDI also says labels from a labeling agency go on both rated doors and rated frames, and it points to NFPA 80, the standard for fire doors, for installation, inspection and maintenance. For a takeoff, that means a rated opening is priced as a labeled door, a labeled frame and hardware that suits it, not just a door with a number in the rating column.

What is a hardware set on a door schedule?

The hardware column holds a group number, not a list. Allegion describes it as the number that relates to a set of hardware in specification Section 08 71 00, Door Hardware. The spec section spells out each set: hinges, lockset or exit device, closer, stops, seals and so on.

So you count doors per set, then multiply by the items in that set. If set 3 has three hinges and a closer, and four doors use set 3, that is 12 hinges and 4 closers.

How do you do a door takeoff from the schedule?

  1. Count the door tags on every floor plan and compare the total with the number of schedule rows.
  2. Count leaves by size and door type. A pair is two leaves on one row.
  3. Count frames by frame type and material.
  4. Count openings per hardware set, then expand each set from the spec.
  5. Pull out the fire-rated openings and note their ratings.
  6. Measure trim and paint for the doors that need them.

Running the sample schedule through those steps gives this:

ItemFrom marksQty
Type A door, WD-SC, 3070101, 102, 1043 EA
Type B door, HM, 30701031 EA
Type C door, WD-SC, 3070 leaves105 (pair)2 EA
Type D door, AL storefront1061 EA
Frame F1, HM single101, 102, 103, 1044 EA
Frame F2, HM pair1051 EA
Frame F3, AL1061 EA
Hardware set 3101, 1022 openings
Hardware sets 1, 4, 5, 7106, 105, 103, 1041 opening each
Rated openings101, 102 at 20 min; 103 at 45 min3 openings

That is 6 openings and 7 leaves. If the plans show 7 tags and the schedule has 6 rows, stop and find the missing door before you go further. The same counting habits apply to outlets and fixtures, as covered in count takeoff.

How much casing does a door need?

Casing only applies where the frame calls for it, typically a wood jamb. Hollow metal frames like F1 in the sample get none. For a cased door, each side of the wall gets two legs and one head.

Head: 32 inLeg: 80 inLeg: 80 in2868FloorAdd a cutting allowance to each piece

Worked example for a 2868 door (32 by 80 inches), using a 6 inch allowance per piece for the miters and cuts. The allowance is an assumption for this example, so use your own figure:

An exterior door may only be cased on the inside, so check the details before you double. Add your waste factor on its own line.

Do you take off paint per door?

Only for doors the schedule or spec says are field finished. Factory-finished and aluminum doors carry no paint line. In the sample, door 103 is marked field paint.

A simple way to carry it is face area: a 3070 leaf is 3 x 7 = 21 SF per face, so 42 SF for both faces, edges ignored. Frames are simpler to carry as a count. Painters who price by the door can skip the area and use the count. More on pricing that work is in painting estimating software.

Counting doors on the PDF

In MeasureFloorPlan's Takeoff mode, the Count tool (shortcut C) adds one click per item, with a Doors category ready to use and Other for custom names such as "Type A 3070" or "HW set 3". The counts land in the takeoff table and in the CSV, Copy table and PDF exports. Distance runs can be grouped into named line items with subtotals, which suits casing.

The window side of the set works the same way. See how to read a window schedule for rough openings, glazing values and wall deductions.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

Frequently Asked Questions

What is a door schedule in construction?

It is a table in the drawings that lists every door opening by its mark, with the size, thickness, door type, materials, frame, fire rating, hardware set and remarks. The mark on the floor plan tells you which row describes that door.

What does 3070 mean on a door schedule?

It is shorthand for a door 3 feet 0 inches wide by 7 feet 0 inches tall. The first two digits are the width in feet and inches and the last two are the height, the same way a 3068 is 3 feet 0 inches by 6 feet 8 inches (36 by 80 inches).

What do HM, WD and SC mean on a door schedule?

HM is hollow metal, WD is wood and SC is solid core, so WD-SC is a solid core wood door. AL is aluminum and GL is glass. Codes vary between offices, so check the abbreviation list in the set before you price anything.

What is a hardware set on a door schedule?

It is a number or code, such as 3 or HW-3, that points to a list of hardware in the specifications (Section 08 71 00, Door Hardware). Every door with the same set number gets the same hinges, lockset, closer, stops and seals.

Does a blank fire rating mean the door is not rated?

Usually. Allegion notes that non-rated openings may be shown as 0, NON or a blank cell. If the wall around the door is rated and the cell is blank, send a question to the architect before you bid.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.