Construction abbreviations are the short codes architects and engineers write on blueprints to save space: TYP for typical, AFF for above finished floor, OC for on center. The list below groups the common ones by trade, but the abbreviation list inside the plan set you are bidding always wins. It is one of the first things to check when you read blueprints for a takeoff.
Measure Plans in Minutes
Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.
A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.
Where do you find the abbreviations in a plan set?
Check the general sheets at the front of the set first. That is where the cover, sheet index, symbols legend and general notes live, and the abbreviation list usually sits with them. A 2025 University of Maine bid set, for example, puts symbols and abbreviations on sheet GI002, right after the cover sheet.
Some owners split the list by discipline. The Department of Veterans Affairs, for one, publishes plumbing abbreviations separately from its architectural ones, so check the first sheet of each trade too. If you are not sure which sheets come first, see what each sheet in a construction plan set is for.
Is there one standard list of blueprint abbreviations?
Not one that every office follows. The U.S. National CAD Standard, published by the National Institute of Building Sciences, includes a Uniform Drawing System with its own terms and abbreviations file. Agencies and firms also keep house lists, and they do not always agree.
The Department of Veterans Affairs is a good example. Its architectural abbreviation sheets use ACT for acoustical ceiling tile and GYP BD for gypsum board. Its finish schedule spec (section 09 06 00) uses AT for the same ceiling tile and GWB for gypsum wallboard, and reserves CPT for carpet modular tile. Same agency, two codes. Punctuation also varies: some sets write A.F.F. and V.I.F. with periods, while the VA sheets drop them.
Construction abbreviations list by category
These are architectural drawing abbreviations most estimators run into, grouped the way you meet them on the sheets. Where an abbreviation has more than one meaning, the second one is in parentheses, and the sheet it appears on tells you which applies.
| Abbreviation | Meaning | Source |
|---|---|---|
| General and dimensions | ||
| AFF | Above finished floor | VA |
| APPROX | Approximate | VA |
| BOT | Bottom | VA |
| CL | Center line | VA |
| CLR | Clear | VA |
| DET | Detail | VA |
| DIM | Dimension | VA |
| DWG | Drawing | VA |
| EL | Elevation | VA |
| EQ | Equal | VA |
| EXIST | Existing | VA |
| HT | Height | VA |
| MAX / MIN | Maximum / minimum | VA |
| NIC | Not in contract | VA |
| NOM | Nominal | VA |
| NTS | Not to scale | W |
| OC | On center | VA |
| REQD | Required | VA |
| SCHED | Schedule | VA |
| SECT | Section | VA |
| SHT | Sheet | VA |
| SIM | Similar | VA |
| THK | Thickness | VA |
| TYP | Typical | VA |
| UNO | Unless noted otherwise | W |
| VIF | Verify in field | VA |
| Quantities and units | ||
| EA | Each | VA |
| LF | Linear feet | WSDOT |
| SF | Square foot (feet) | VA |
| SQ YD | Square yard | VA |
| CU YD | Cubic yard | VA |
| QTY | Quantity | VA |
| PR | Pair | VA |
| Materials | ||
| ALUM | Aluminum | VA |
| CMU | Concrete masonry unit | VA |
| CONC | Concrete | VA |
| GALV | Galvanic or galvanized | VA |
| GL | Glass | VA |
| GYP BD | Gypsum board | VA |
| GWB | Gypsum wallboard | VA-F |
| INSUL | Insulation | VA |
| MTL | Metal | VA |
| PLAM | Plastic laminate | VA |
| PLYWD | Plywood | VA |
| STL | Steel | W |
| WD | Wood | VA |
| Doors and windows | ||
| DR | Door (also drain or dressing room) | VA |
| DR FR | Door frame | VA |
| DR OPNG | Door opening | VA |
| DBL GLZ | Double glaze | VA |
| HC | Hollow core | VA |
| HDR | Header | VA |
| HM | Hollow metal (also hectometer) | VA |
| LVR | Louver | VA |
| MO | Masonry opening or motor | VA |
| RO | Rough opening | VA |
| SC | Solid core (also shading coefficient) | VA |
| WDW | Window | VA |
| Structural | ||
| BM | Beam or benchmark | VA |
| BRG | Bearing | VA |
| COL | Column | VA |
| EJ | Expansion joint | VA |
| FTG | Footing | VA |
| REINF | Reinforce | VA |
| STL JST | Steel joist | VA |
| STRUCT | Structural | VA |
| TO FDN | Top of foundation | VA |
| TOS | Top of steel | VA |
| TOW | Top of wall | VA |
| WWF | Welded wire fabric | VA |
| Mechanical, electrical and plumbing | ||
| AHU | Air handling unit | VA |
| DIFF | Diffuser (also difference) | VA |
| ELEC | Electric | VA |
| FA | Fire alarm | VA |
| FD | Floor drain | VA |
| HB | Hose bibb | VA |
| HVAC | Heating, ventilating and air conditioning | VA |
| J-BOX | Junction box | VA |
| LAV | Lavatory | VA |
| LTG | Lighting | VA |
| MECH | Mechanical | VA |
| PLBG | Plumbing | VA |
| RECPT | Receptacle | VA |
| SD | Smoke detector (also shop drawings) | VA |
| SW | Switch | VA |
| VTR | Vent through roof | VA |
| WC | Water closet (also wall covering) | VA |
| WH | Water heater | VA |
| Finishes | ||
| ACT | Acoustical ceiling tile | VA |
| CLG | Ceiling | VA |
| CLG HT | Ceiling height | VA |
| CPT | Carpet | VA |
| CT | Ceramic tile | VA |
| FIN | Finish | VA |
| FIN FLR | Finish floor | VA |
| FOF | Face of finish | VA |
| FOS | Face of slab or face of stud | VA |
| PT | Paint | VA |
| RB | Resilient base or rubber base | VA |
| RCP | Reflected ceiling plan | VA |
| SUSP CLG | Suspended ceiling | VA |
| VCT | Vinyl composition tile (also vitrified clay tile) | VA |
VA: Department of Veterans Affairs architectural abbreviation standard detail sheets (SD000115, December 2008). VA-F: VA specification section 09 06 00, Schedule for Finishes. W: Wikipedia, Engineering drawing abbreviations and symbols. WSDOT: Washington State DOT Terminal Design Manual, Appendix A.
Which abbreviations change your takeoff?
Most abbreviations just name a thing. A handful tell you how far a note reaches, whether you can trust the drawing, or whether the work is yours at all. Those are the ones that move quantities.
- TYP means one note covers every matching spot. You still count every spot.
- SIM means built like the referenced condition, with differences. Find them before you copy numbers.
- UNO sets a default. Everything follows the note unless the drawing says otherwise somewhere else.
- NTS means do not scale the view. Use the written dimensions only.
- VIF means the dimension must be checked on site. Carry an allowance or list it as an assumption.
- NIC means not in contract. Leave it out and name it in your exclusions.
- OC gives spacing, which turns a wall length into a count of studs, joists or fasteners.
- AFF and CLG HT give heights, which turn wall lengths into wall area.
The Wikipedia list of engineering drawing abbreviations even flags UNO as one to spell out to avoid confusion. When a note is that easy to misread, a quick RFI costs less than a bad bid.
Heights marked AFF or CLG HT are measured up from the floor, which is easiest to see in a cut through the building. For how those vertical dimensions show up, see how to read a section drawing.
Worked example: reading an abbreviated wall note
Say a partition on the floor plan carries this note: 2x4 WD STUDS @ 16" OC, GYP BD EA SIDE, TYP. The wall is 24 feet long and the room schedule gives a CLG HT of 9'-0". Spelled out, that is 2x4 wood studs at 16 inches on center with gypsum board on each side, and the same build applies at every similar wall.
| Item | Math | Quantity |
|---|---|---|
| Stud spaces | 24 ft x 12 in / 16 in OC | 18 spaces |
| Studs | 18 spaces + 1 end stud | 19 EA |
| Plates | 24 LF x 2 (top and bottom) | 48 LF |
| Gypsum board | 24 LF x 9 ft x 2 sides | 432 SF |
That count is layout only. Corners, openings and any double top plate called for in the details get added on top. The TYP is what makes this note matter: if ten similar walls total 180 LF, the board alone is 180 x 9 x 2 = 3,240 SF, all from one short note.
Keep units consistent while you do this. LF, SF, SQ YD and CU YD all appear on drawings and in specs, and the construction units of measure guide covers how to convert between them.
Abbreviations vs symbols on drawings
Abbreviations are text. Symbols are graphics: door swings, section cut marks, outlet and switch marks, material hatches. The Maine set above puts both on one general sheet, but they are still separate legends. For the graphic side, use this architectural symbols reference.
Measuring once you can read the notes
Once the notes make sense, the measuring is the slow part. In MeasureFloorPlan you upload the whole PDF set, set the scale on each sheet from one printed dimension, then click runs for linear feet, trace rooms for floor, wall and ceiling area, and count fixtures and outlets. The takeoff exports to Excel or PDF. More on that in blueprint reading software.
Measure Plans in Minutes
Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.
A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.
Frequently Asked Questions
Is there a standard list of construction abbreviations?
There are published lists, such as the terms and abbreviations that come with the U.S. National CAD Standard and the architectural abbreviation sheets from the Department of Veterans Affairs. No single list binds every architect, though. The abbreviation list in the plan set you are bidding is the one that counts.
What does TYP mean on a drawing?
TYP means typical. A note or dimension marked TYP applies to every similar condition on the sheet, not just the one it points at. For a takeoff, that usually means one note covers many locations you still have to count.
What is the difference between TYP and SIM?
TYP says the same thing repeats as drawn. SIM means similar, so the condition is built like the referenced one but is not identical. Check what differs before you copy quantities from one SIM location to another.
Where are the abbreviations on a set of plans?
Look at the general sheets at the front of the set, the ones with the cover, sheet index, symbols and general notes. Some owners also keep separate lists by trade, so check the first sheet of the plumbing, mechanical and electrical drawings too.
What does NIC mean in construction?
NIC means not in contract. Work marked NIC is shown for reference but is not part of the bid, so leave it out of your quantities and say so in your bid exclusions.