MeasureFloorPlan

Home › Learn › Room Finish Schedule: How to Read It and Take Off Every Finish

Part of: What Is a Takeoff in Construction? How to Do One From Plans

Room Finish Schedule: How to Read It and Take Off Every Finish

Room Finish Schedule: How to Read It and Take Off Every Finish

A room finish schedule is the table that tells you what goes on the floor, base, walls and ceiling of every room in the building. You read it across one row per room, look up each code in the finish legend, then measure the rooms on the floor plan to get square feet and linear feet for each finish. It is one of the schedules you meet when you read blueprints for construction, and for flooring, paint and ceiling trades it is the sheet that decides what you are pricing.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

What is a finish schedule?

A finish schedule lists every room by number and name, with a finish code for each surface. The codes are short tags like CPT-1 or PT-2, and each one is described once in a finish legend or in the specification, with the product, color and sheen.

The schedule does not give you any quantities. It tells you what each surface gets. The quantities come from the floor plan, the ceiling heights and your own measuring.

Where is the finish schedule in a plan set?

Start at the sheet index on the cover sheet. Under the U.S. National CAD Standard sheet numbering, the digit after the discipline letter is the sheet type, and type 6 is schedules and diagrams. So on an architectural set the finish schedule often sits on an A-6xx sheet, next to the door and window schedules.

That is a convention, not a rule. Smaller sets often put the schedule right on the floor plan sheet, and interiors-heavy jobs may carry a separate finish plan on I-sheets. A finish plan shows the same finishes as hatches or tags drawn on the plan, which helps where a floor pattern or a transition needs to be seen, not just named.

What columns are on a room finish schedule?

Layouts vary by office, but most schedules carry these typical columns. Your project's schedule and legend always win over any general description.

Here is a short sample schedule for four rooms. The codes and rooms are made up for teaching; they are not from any real project or standard.

Sample room finish schedule (illustration only)
RoomNameFloorBaseNorthEastSouthWestCeilingClg htRemarks
101OfficeCPT-1RB-1PT-2PT-1PT-1PT-1ACT-19'-0"North wall is accent
102OfficeCPT-1RB-1PT-1PT-1PT-1PT-1ACT-19'-0"
103Break roomLVT-1RB-1PT-1PT-1PT-1PT-1GWB-19'-0"Ceiling painted PT-1
104CorridorLVT-1RB-1PT-1PT-1PT-1PT-1ACT-19'-0"

Sample only. Real schedules may add columns for wainscot, ceiling finish separate from ceiling material, or a finish plan reference.

How do finish codes and the finish legend work?

The code is a material prefix plus a number. The prefix says what kind of finish it is; the number tells one product apart from another of the same kind. CPT-1 and CPT-2 are both carpet, but they can be different products at different prices. Always price by the full code.

The legend for the sample schedule above might read like this:

Sample finish legend (illustration only)
CodeSample descriptionTakeoff unit
CPT-1Carpet tile, 24 x 24 inSF
LVT-1Luxury vinyl tileSF
RB-1Rubber base, 4 inLF
PT-1Paint, field color, eggshellSF
PT-2Paint, accent color, eggshellSF
ACT-1Acoustic ceiling tile, 2 x 2 ft, in suspended gridSF
GWB-1Gypsum wall board ceiling, paintedSF

A real legend also names the manufacturer, product line, color and the spec section. If a code on the schedule is missing from the legend, or the legend and spec disagree, write an RFI before you bid it.

Finish schedule abbreviations to know

The prefixes come from the abbreviations list on the general sheet. The Archtoolbox abbreviations list gives ACT as acoustic ceiling tile, CPT as carpet, CT as ceramic tile, GWB as gypsum wall board, PNT as paint or painted, and AFF as above finished floor. RB shows up on many sets as resilient or rubber base.

Watch for collisions. That same list gives PT as pressure treated, while plenty of finish legends use PT for paint. Abbreviations vary from office to office, so the legend on your set is the only one that counts.

How do room numbers tie the schedule to the floor plan?

Every room on the floor plan carries a room tag with its number and name. The schedule row with the same number is that room. To take off a finish, you find the room on the plan by its tag, measure it, and enter the result against the codes in that row.

Wall columns marked North, East, South and West follow the plan's north arrow, so check which way it points before you assign an accent wall. If you need a refresher on room tags and plan symbols, see how to read a floor plan. Ceiling codes and heights should match the reflected ceiling plan; when they don't, ask which one governs.

How do you take off quantities from a finish schedule?

Each column turns into one kind of quantity.

  1. Floor: measure each room's floor area in SF, then add up the rooms by floor code.
  2. Base: measure each room's perimeter in LF, subtract door openings, and total by base code.
  3. Walls: multiply each wall's length by the ceiling height from the schedule to get SF, and total by paint or wall finish code.
  4. Ceiling: for a flat ceiling, the ceiling area equals the floor area. Total by ceiling code.
  5. Remarks: read every remark and pull any extra item (accent wall, wainscot, existing to remain) onto its own line.
  6. Add waste per material at the end, not room by room.

Finish schedule example: a worked takeoff

Take the four sample rooms. Office 101 is 12 x 14 ft, Office 102 is 12 x 12 ft, Break Room 103 is 10 x 15 ft and Corridor 104 is 6 x 30 ft. Each office and the break room has one 3 ft wide door into the corridor, and the corridor has one more 3 ft door at its end. Doors are 3 x 7 ft.

Floor by code. CPT-1 covers 101 and 102: 12 x 14 = 168 SF plus 12 x 12 = 144 SF, so 312 SF. LVT-1 covers 103 and 104: 10 x 15 = 150 SF plus 6 x 30 = 180 SF, so 330 SF.

Base, RB-1 everywhere. Perimeters are 52 LF (101), 48 LF (102), 50 LF (103) and 72 LF (104). A door in a shared wall breaks the base on both sides, so the corridor loses 3 room doors plus its end door, 12 LF in all. Each room loses 3 LF. That gives 49 + 45 + 47 + 60 = 201 LF of RB-1.

Walls by color, using perimeter x the 9 ft ceiling height. The accent is only the north wall of 101, which is 12 ft long: 12 x 9 = 108 SF of PT-2. The rest of 101 is 14 + 12 + 14 = 40 LF, so 360 SF. Add 102 (48 x 9 = 432), 103 (50 x 9 = 450) and 104 (72 x 9 = 648) and PT-1 comes to 1,890 SF gross. Seven door faces at 21 SF each take off 147 SF, leaving 1,743 SF net of PT-1 (assuming the door in 101 is not on the accent wall).

Ceilings by type. ACT-1 covers 101, 102 and 104: 168 + 144 + 180 = 492 SF. GWB-1 covers 103: 150 SF, and the remark says it gets painted, so 150 SF of PT-1 goes on a ceiling line too. As a check, 492 + 150 = 642 SF, the same as the floor total.

CodeSurfaceRoomsNet quantity
CPT-1Floor101, 102312 SF
LVT-1Floor103, 104330 SF
RB-1BaseAll201 LF
PT-1WallsAll1,743 SF
PT-2Walls101 north108 SF
PT-1Ceiling103150 SF
ACT-1Ceiling101, 102, 104492 SF
GWB-1Ceiling103150 SF

These are net numbers. Add waste per material from your own history or published construction waste factors, then round up to cartons, gallons and boxes.

What gets missed when reading a finish schedule?

Measuring the rooms faster

The slow part is not reading the schedule. It is measuring every room for area and perimeter. In MeasureFloorPlan, one trace per room gives floor area, perimeter in linear feet, and wall and ceiling area from your ceiling height. The quantities table exports to Excel (CSV) or PDF, and from there you total the rooms by finish code. For a paint-only bid, see painting estimating software for wall and ceiling area from the same trace.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

Frequently Asked Questions

What is a finish schedule in construction?

It is a table in the drawings that lists every room and the finish on its floor, base, walls and ceiling, usually with the ceiling height and a remarks column. Each finish is written as a short code that a legend or the specification spells out.

What is the difference between a finish plan and a finish schedule?

A finish plan shows finishes graphically on the floor plan, with hatches or tags and a legend. A finish schedule lists the same information room by room in a table. Many sets use both: the schedule covers every room and the plan shows patterns and transitions.

Where is the finish schedule in a set of drawings?

Look at the sheet index first. Under the U.S. National CAD Standard numbering, sheet type 6 is schedules and diagrams, so an architectural schedule sheet is often numbered in the A-600 range. Some sets put it on the finish plan or interiors sheets instead.

What do the abbreviations on a finish schedule mean?

The project legend defines them. Common ones include ACT for acoustic ceiling tile, CPT for carpet, CT for ceramic tile and GWB for gypsum wall board. Abbreviations vary from office to office, so read the legend on your set rather than going from memory.

What does a finish schedule look like?

Rows are rooms, listed by room number. Columns run left to right through floor, base, walls (sometimes one column per wall), ceiling, ceiling height and remarks. The cells hold finish codes such as CPT-1 or PT-2 rather than full product names.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.