A count takeoff is the part of a takeoff where you tally items priced by the piece: doors, windows, outlets, switches, light fixtures, plumbing fixtures and the like. To do one, count a single symbol type at a time, sheet by sheet, mark each symbol as you count it, and check your total against the legend and any schedule.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

What is a count takeoff?

It is a list of every countable item on the plans, with a total for each type. Counts are recorded in EA (each). Unlike square feet or linear feet there is nothing to convert, which is covered in more detail under construction units of measure.

Counting sounds like the easy part. It is also where bids quietly lose money, because one missed fixture type repeated across a building adds up fast. Estimators sometimes call it an each takeoff or a piece count takeoff. Same job.

What items go on a count takeoff?

Anything you buy, install or price by the unit. The table lists common count items by trade and the sheets you would normally look at first. Your drawing index tells you which sheets a given set actually has.

Count itemWhere to look first
Doors and windowsFloor plans, then the door and window schedules
Receptacles (outlets) and switchesElectrical power plans
Light fixturesReflected ceiling plan or electrical lighting plan, plus the fixture schedule
Toilets, sinks, tubs, water heatersFloor plans and plumbing sheets, plus any plumbing fixture schedule
HVAC supply and return diffusersReflected ceiling plan and mechanical sheets
Sprinkler headsFire protection sheets, if the set includes them
Anchor bolts, hold-downs, embedsFoundation and structural sheets

Where do counts come from on a plan set?

Most counts live on more than one sheet. A floor plan shows doors and windows and may show fixtures such as sinks, water heaters and furnaces. The reflected ceiling plan, a variation of the floor plan, shows lighting and the mechanical features you can see in the ceiling, which is why lights and diffusers get counted there.

Electrical sheets are their own layer. An electrical drawing uses lines, symbols, dimensions and notes to show power, lighting and communication, with floor plans showing where the electrical systems sit on every floor. Price outlets and switches from those sheets, even when the architectural floor plan shows a few of them too.

Schedules are the cross-check. A door schedule, window schedule or fixture schedule lists each type once with its mark, so comparing your symbol count with it catches misses in both directions. Read the schedule for what each type is, and count the plan for how many there are.

How to count outlets on blueprints (and other symbols)

Open the legend before you count anything. Symbols vary between offices and projects, and the legend on the first electrical sheet is what tells you which mark is a duplex receptacle, which is a GFCI and which is a dedicated circuit. If you need a refresher on common marks, keep an architectural symbols reference open, but the project legend always wins.

BEDROOM 1Sheet E-10112345LEGENDDuplexoutletCountedmarkOutlets5 EASymbol drawn per this sample legend. Use the legend on your own set.

In the diagram, each outlet gets a number the moment you count it. When you reach the end of the room you have 5 marks and 5 EA, and any symbol without a mark is one you skipped. The same 5 outlets show up as the last line of the worked example on the takeoff sheet guide.

How to count items on a plan without double counting

  1. Pull every sheet that can hold your items, using the drawing index, and note the revision date.
  2. Read the legend and any schedules so you know each symbol and type before you start.
  3. Pick one symbol type, such as duplex outlets, and count only that type.
  4. Go sheet by sheet in a fixed order, and mark each symbol on the plan as you count it.
  5. Write the subtotal for that sheet with its sheet number before moving to the next one.
  6. Watch for TYP. notes and repeated unit plans; count the typical unit once and multiply.
  7. Repeat for the next symbol type until every item in the legend has a line.
  8. Compare totals with the schedules and with a rough check, such as doors per unit.

Steps 3 and 4 do most of the work. Counting outlets, switches and lights in one pass feels faster, but your eye starts jumping between symbols and that is when items get skipped. Double counts usually happen where a room is split across two sheets or where matchlines overlap, a pattern covered in common takeoff mistakes.

What does TYP. mean, and how do repeated units change the count?

TYP. stands for typical. In drafting it means other features share the same characteristic, so one labeled item stands in for every similar one, according to the engineering drawing abbreviations list. The same entry notes that newer dimensioning standards prefer an explicit count like 8X over a bare TYP.

On a count takeoff, a TYP. note means the drawing may show the item once while the job needs it many times. Apartment and hotel sets do the same thing at a bigger scale: they draw an enlarged unit plan once and point to it from every floor. Count the enlarged unit, then multiply by the number of times that unit appears on the floor plans.

Count takeoff example: a 12-unit building

Say a three-story building has 8 Unit A apartments and 4 Unit B apartments, each drawn once as an enlarged unit plan. You count each unit plan once, multiply, then add the items in the corridors that sit outside the units.

ItemPer Unit AUnit A x 8Per Unit BUnit B x 4CorridorsTotal
Duplex outlets1411218726190 EA
Interior doors648832080 EA
Recessed lights1080135212144 EA
Toilets1828016 EA

The outlet line works like this: 14 × 8 = 112, 18 × 4 = 72, and 112 + 72 + 6 = 190. Recessed lights: 10 × 8 = 80, 13 × 4 = 52, plus 12 in the corridors, for 144. Doors and toilets follow the same pattern.

Now the check. With one toilet per Unit A and two per Unit B you expect 16, and the plumbing fixture schedule should agree. If the door schedule lists 82 interior doors against your 80, two doors are hiding somewhere, maybe a closet pair on the floor plan that the enlarged unit plan leaves out. Find them before you price.

How should you record counts on a takeoff sheet?

One line per item type, with the sheet number, the location, the count and EA as the unit. For repeated units, write the math on the line (14 per unit × 8) so a reviewer can see the multiplier instead of just a total. Keep spares out of the counted number and put them in the notes if you carry any.

A count needs no scale, since a symbol is one item at any print size. The lengths and areas on the same sheet do, so read the scale before you move on to them; see how to read an architectural scale. When the counts are done, tick them off on your takeoff checklist before the numbers go into the estimate.

How to do a count takeoff on a PDF

On a PDF you click each symbol instead of ticking it with a pencil, and the software keeps the tally. If you are new to digital plans, start with how to do a takeoff from a PDF, and if a symbol is hard to place in the room layout, see how to read a floor plan.

In MeasureFloorPlan, switch to Takeoff mode and pick the Count tool (keyboard shortcut C). You click once per item. Quick categories cover Doors, Windows, Outlets and Fixtures, and Other takes a custom name, such as diffusers or GFCI outlets. Every sheet of a PDF set is part of one plan.

The counts land in the takeoff table next to your lengths and areas, and they go out with the CSV, Copy table and PDF exports. It is built for PDF plan takeoff on the sets contractors already get from architects and GCs, and it works as takeoff software for contractors who also need lengths and areas. There is a free demo on a sample plan; Starter is $9 a month for 3 plans and Pro is $29 a month unlimited.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

Frequently Asked Questions

What is a piece count takeoff?

It is another name for a count takeoff. You tally items priced by the piece, such as doors, outlets, light fixtures and toilets, and record each total in EA (each) instead of measuring a length or an area.

How do you count light fixtures on a plan?

Start with the reflected ceiling plan or the lighting plan, not the floor plan. Read the fixture legend or schedule first, then count one fixture type at a time across every sheet, marking each symbol as you go, and write a separate line for each type.

Should you add waste to a count?

Usually not. A plan showing 14 outlets means 14 devices. Spares for small, cheap parts are a buying decision, so if you carry extras, put them on their own line or in the notes so the counted number stays clean.

How do you count doors in a plan set?

Count the door tags or swings on the floor plans one floor at a time, then compare your total with the door schedule if the set has one. If the two disagree, find the door that is on one and not the other before you price anything.

What is an electrical takeoff count?

It is the count portion of an electrical takeoff: receptacles, switches, light fixtures, panels and other devices tallied by type from the electrical sheets. Wire and conduit are measured separately in linear feet.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.