A lumber takeoff lists every piece of framing a job needs: studs, plates, headers, sheathing, joists and rafters. For walls, you measure linear feet of each wall type from the floor plan, count studs from the spacing, add studs for corners, intersections and openings, then turn plate footage into pieces and wall area into sheets.
Measure Plans in Minutes
Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.
A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.
What goes on a lumber takeoff?
A framing takeoff follows the way the building goes up. The BYU-Idaho framing estimating guide splits it into floor framing, exterior walls, interior walls, door and window headers, stairs and roof framing. Most of the counting happens in the walls, so the worked example below covers those.
| Item | Measured as | Ordered as |
|---|---|---|
| Wall studs | LF of wall, spacing, corners, intersections, openings | Pieces of a set length (EA) |
| Bottom and top plates | LF of wall × number of plates | Pieces of a stock length |
| Headers | EA per opening, length from the rough opening | Pieces cut from stock lengths |
| Wall sheathing | Wall length × sheathing height (SF) | 4 by 8 sheets |
| Floor joists, rafters, trusses | Count from the framing plans, by length | Pieces or trusses (EA) |
Which sheets do you take framing off?
Wall lengths come from the floor plan. Wall heights, plate counts and sheathing come from the wall sections, and stud size and spacing from the wall type legend or the framing notes. Openings come from the window schedule and door schedule, and header sizes from the structural sheets or a header schedule.
Keep each wall type on its own line. The BYU-Idaho text separates exterior walls, garage walls, common walls, 2x4 and 2x6 interior walls, tall walls and rake walls, because each can have a different stud, spacing, height or sheathing. In the specs, rough carpentry sits under MasterFormat Division 06, Wood, Plastics, and Composites.
How to estimate studs for a wall
Start with the on-center studs. Convert the wall length to inches, divide by the spacing, round up, and add one stud to close the far end. A 12 foot wall at 16 inches on center is 144 / 16 = 9 spaces, so 10 studs.
This is an estimating count, not a stud-by-stud layout. Each wall is counted with its own end studs, and the real layout shifts with the corner detail and where openings land. The allowances below are there to cover those differences without drawing every stud.
Then add the extras. The BYU-Idaho framing chapter uses these allowances:
- 2 studs for each corner or wall intersection.
- 2 studs for each window or door opening less than 6 feet wide, for the trimmers. The king studs come from on-center studs left out of the opening.
- 6 studs for each window 6 feet or wider, since code generally requires double trimmers under those headers. Wide doors get no extra, because the studs left out of the opening cover the trimmers.
Wall height sets the stud length. The same text names 92 5/8 inches as the typical wall stud, and it frames its sample walls with a single bottom plate and a double top plate. At an actual 1 1/2 inches per plate, 92 5/8 + 3 × 1 1/2 = 92 5/8 + 4 1/2 = 97 1/8 inches, or 8 feet 1 1/8 inches of wall.
Framing takeoff example: a 48 by 32 foot building
A sample one-story building on a slab, 48 by 32 feet. Exterior walls are 2x4 at 16 inches on center with a single bottom plate and double top plate. The plan shows 4 corners and 6 places where interior walls tee into the exterior walls. The schedules list ten 3 by 4 foot windows and two 3 foot doors, all under 6 feet wide.
Studs, wall by wall:
- Each 48 foot wall: 48 × 12 = 576 inches, 576 / 16 = 36 spaces, so 37 studs.
- Each 32 foot wall: 32 × 12 = 384 inches, 384 / 16 = 24 spaces, so 25 studs.
- On-center total: 37 + 37 + 25 + 25 = 124 studs.
- Corners: 4 × 2 = 8. Intersections: 6 × 2 = 12.
- Openings under 6 feet: (10 windows + 2 doors) × 2 = 12 × 2 = 24.
- Total: 124 + 8 + 12 + 24 = 168 studs.
- At an example 5% waste: 168 × 1.05 = 176.4, so 177 precut studs.
Plates use the BYU formula: wall length × number of plates × (1 + waste) / stock length. The bottom plate sits on concrete, and the BYU text calls for pressure treated or other rot resistant plate there, so it gets its own line.
| Item | Math | Order |
|---|---|---|
| Studs, 2x4 × 92 5/8 in | 124 on-center + 8 + 12 + 24 = 168; × 1.05 = 176.4 | 177 EA |
| Bottom plate, treated 2x4 × 16 ft | 160 LF × 1 × 1.05 / 16 = 10.5 | 11 EA |
| Top plates, 2x4 × 16 ft | 160 LF × 2 × 1.05 / 16 = 21 | 21 EA |
| Headers, 2-ply 2x8 (example size) | 12 openings × 2 plies = 24 pieces at 39 in. A 14 ft board is 168 in, and 168 / 39 = 4.3, so 4 per board. 24 / 4 = 6 | 6 EA 2x8 × 14 ft |
| Wall sheathing, 4 × 8 sheets | 160 × 8 = 1,280 SF; 1,280 / 32 = 40; × 1.05 = 42 | 42 sheets |
The perimeter is 2 × (48 + 32) = 160 LF, the same number the insulation takeoff uses for this building, so measure it once and share it. This example treats every opening as a 36 inch rough opening, so each header spans it plus a 1 1/2 inch trimmer on each side: 36 + 3 = 39 inches. Take real rough openings from the schedules. The header size here is only an example; the structural drawings set the real one, plus any spacer the detail shows.
The sheathing line keeps the openings in, which is a judgment call. BYU's method uses wall length × sheathing height, and that height can run past the wall itself, down to the top of the foundation, when the walls sit on a framed floor. The 5% everywhere is an example. Set yours from past jobs or the ranges on the construction waste factors page.
How do you convert a lumber takeoff to board feet?
A board foot is 144 cubic inches, a piece 1 foot long, 1 foot wide and 1 inch thick. Planed softwood is figured at its nominal size, so a 2x4 counts as 2 by 4 even though it is really about 1 1/2 by 3 1/2 inches. Board feet = thickness (in) × width (in) × length (ft) / 12.
- Plates: one 2x4 × 16 ft is 2 × 4 × 16 / 12 = 10.67 BF. 32 pieces × 10.67 = 341.4 BF.
- Headers: one 2x8 × 14 ft is 2 × 8 × 14 / 12 = 18.67 BF. 6 pieces × 18.67 = 112 BF.
- Studs: one 2x4 × 92 5/8 in is 2 × 4 × 7.72 / 12 = 5.15 BF. 177 × 5.15 = 911.6 BF.
If your supplier quotes by the piece, skip this step and order the counts. If they quote by the board foot, the walls in this example come to about 341.4 + 112 + 911.6 = 1,365 BF before sheathing.
Common lumber takeoff mistakes
- Counting studs from the total perimeter and forgetting the end stud on each wall.
- Skipping corners and intersections, which added 20 studs in the example.
- Using regular plate stock where the bottom plate bears on concrete and needs treated lumber.
- Pricing every wall at one height, when tall walls, rake walls and pony walls need different stud lengths.
- Sizing headers by guess instead of from the structural sheets.
- Taking wall lengths off the outside dimension string for interior walls, or measuring from a sheet that is not to scale.
The slab and footings these walls sit on are a separate trade. They go on the concrete takeoff in cubic yards. For more on adding up wall runs, see how to calculate linear feet.
How to do a framing takeoff on a PDF
In MeasureFloorPlan you upload the PDF plan set (every sheet is part of one plan), set the scale from one printed dimension, and click along each wall with the Distance tool. Runs can be grouped into named line items with subtotals, so exterior 2x4, interior 2x4 and 2x6 plumbing walls each get their own total in linear feet.
The Count tool (shortcut C in Takeoff mode) handles windows, doors and other openings, and Other takes a custom name such as corners or intersections. Everything exports to CSV, Copy table or PDF for the stud math above. For quick perimeters the perimeter calculator is free, and for full sets see PDF plan takeoff. There is a free demo on a sample plan; Starter is $9 a month for 3 plans and Pro is $29 a month unlimited.
Measure Plans in Minutes
Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.
A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.
Frequently Asked Questions
How do you calculate how many studs you need for a wall?
Convert the wall length to inches, divide by the stud spacing, round up and add one for the end stud. Then add extras: two for each corner or wall intersection, two for each window or door opening under 6 feet wide, and six for each window 6 feet or wider, the allowances used in the BYU-Idaho construction estimating text.
How many studs per linear foot of wall?
At 16 inches on center, 12 / 16 = 0.75 studs per foot of wall. At 24 inches on center it is 12 / 24 = 0.5. Those are on-center studs only, so corners, intersections and openings are added on top.
What length stud do you use for an 8 foot wall?
A 92 5/8 inch precut stud is the typical wall stud named in the BYU-Idaho estimating text. With a single bottom plate and a double top plate at 1 1/2 inches each, 92 5/8 + 4 1/2 = 97 1/8 inches, a wall height of 8 feet 1 1/8 inches.
How do you calculate board feet of framing lumber?
Multiply the nominal thickness in inches by the nominal width in inches by the length in feet, then divide by 12. A 2x4 that is 16 feet long is 2 × 4 × 16 / 12 = 10.67 board feet. Planed softwood is measured at nominal size even though a 2x4 is really about 1 1/2 by 3 1/2 inches.
How many sheets of OSB do I need for exterior walls?
Multiply the wall length by the sheathing height for square feet, divide by 32 (one 4 by 8 sheet), and round up after adding your waste. A 160 foot perimeter at 8 feet is 1,280 SF, and 1,280 / 32 = 40 sheets before waste.