A concrete takeoff measures every footing, wall, slab and pad on the plans and turns each one into cubic yards: length × width × thickness in feet, divided by 27. Group the lines by pour, add 4% to 10% for contingencies, and round up to what you will actually order from the plant.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

What do you measure in a concrete takeoff?

Every element that gets concrete, each on its own line. Ready mix is sold by volume, in cubic yards of fresh, unhardened concrete, according to the National Ready Mixed Concrete Association guide CIP 31, Ordering Ready Mixed Concrete. So the takeoff ends in CY, even though you measure in feet and inches.

ElementWhat you take off the planWhere it usually is
Continuous (strip) footingsLength along the centerline, plus width and depthFoundation plan, footing schedule, wall sections
Pad (spread) footingsCount of each type, plus length, width and depthFoundation plan, footing schedule
Foundation and stem wallsCenterline length, height, thickness, minus large openingsFoundation plan, sections
Slabs on gradeArea, thickness, thickened edges and depressionsFoundation plan, slab details
Piers and columnsCount, diameter or size, heightFoundation plan, schedules
Sidewalks, driveways, padsArea and thicknessSite plan, civil sheets

Forms, rebar, vapor barrier and anchor bolts usually get their own lines too, in linear feet, pounds, square feet or each. The framing that sits on top of the foundation is a separate job, covered in the lumber takeoff guide.

Which sheets hold the concrete dimensions?

Start with the foundation plan. It shows where the footings and walls run, with gridlines and dimensions, and it usually tags each footing with a mark like F1 or F2. The footing schedule tells you what those marks mean: width, depth and reinforcing for each type.

Thickness lives in the sections and details. A plan view can't show how deep a footing is or where a slab thickens at its edge, so read every cut that touches the foundation. If those are new to you, see how to read a section drawing. Flatwork outside the building (walks, drives, equipment pads) comes from the site plan.

Read the general notes as well. Different parts of a building commonly use different concrete mixtures, NRMCA notes, so a footing at one strength and a slab at another are two separate orders even on the same day.

The concrete takeoff formula: cubic feet to cubic yards

A cubic yard is 27 cubic feet (3 ft × 3 ft × 3 ft). Every concrete line uses the same formula:

Concrete cubic yards = length (ft) × width (ft) × thickness (ft) ÷ 27

Thickness is almost always given in inches, so convert first. Divide inches by 12, or leave the inches in and divide the whole thing by 324 (27 × 12). The table has the common ones.

ThicknessIn feetCY per 100 SF
4 in0.333 ft100 × 0.333 ÷ 27 = 1.23
5 in0.417 ft100 × 0.417 ÷ 27 = 1.54
6 in0.5 ft100 × 0.5 ÷ 27 = 1.85
8 in0.667 ft100 × 0.667 ÷ 27 = 2.47
10 in0.833 ft100 × 0.833 ÷ 27 = 3.09
12 in1 ft100 × 1 ÷ 27 = 3.70

For a quick check on any single shape, the volume calculator gives cubic feet and cubic yards from three dimensions.

How do you measure footings and walls without double counting the corners?

Measure them on the centerline. If you take the outside dimensions of the building and run them all the way around, each corner gets counted twice, because the two walls overlap there. The centerline length counts each corner once.

For a rectangle the fix is simple. Take the outside perimeter and subtract four times the wall thickness. A 40 ft × 28 ft building with an 8 inch wall has an outside perimeter of 136 ft. Four times 8 inches is 32 inches, or 2.67 ft, so the centerline is 136 - 2.67 = 133.33 LF. On an L or U shaped plan, add up the centerline of each straight run instead.

GradeSlab on grade, 4 inInsideOutsideCenterline (measure length here)Wall 8 in thickWall 3 ft tallFooting 20 in wide10 in deep

The section above is the foundation used in the worked example below. The footing is centered under the wall, so the footing and the wall share the same 133.33 LF centerline.

Concrete takeoff example: a 40 × 28 foundation

Say the foundation plan shows a 40 ft × 28 ft building (outside dimensions) on the section above, plus four interior pad footings marked F2 at 3 ft × 3 ft × 12 in. The slab sits inside the walls, so it measures 40 - 1.33 = 38.67 ft by 28 - 1.33 = 26.67 ft (two 8 inch walls come off each direction).

  1. Footing F1: 133.33 LF × 1.667 ft × 0.833 ft = 185.19 CF. 185.19 ÷ 27 = 6.86 CY.
  2. Pads F2: 3 × 3 × 1 = 9 CF each. 9 × 4 = 36 CF. 36 ÷ 27 = 1.33 CY.
  3. Wall: 133.33 LF × 0.667 ft × 3 ft = 266.67 CF. 266.67 ÷ 27 = 9.88 CY.
  4. Slab: 38.67 × 26.67 = 1,031.11 SF. 1,031.11 × 0.333 = 343.70 CF. 343.70 ÷ 27 = 12.73 CY.
  5. Total plan volume: 6.86 + 1.33 + 9.88 + 12.73 = 30.80 CY.

That 30.80 CY is the neat volume. It's what the drawings say, not what you order.

How much concrete do you order? Overage and rounding

NRMCA says the quantity ordered should be 4% to 10% more than an estimate calculated from the plan dimensions, to account for contingencies. Uneven subgrade, a trench dug wide, forms that bow a little and spillage all eat into the neat number. For waste on other materials, see construction waste factors.

Apply the overage per pour, because each pour is its own order. In the example the footings and pads go in first, the wall second and the slab last. At an example 7% overage, rounded up to the next half yard:

PourPlan volume× 1.07Order
Footings + pads6.86 + 1.33 = 8.19 CY8.76 CY9.0 CY
Foundation wall9.88 CY10.57 CY11.0 CY
Slab on grade12.73 CY13.62 CY14.0 CY
Total30.80 CY32.96 CY34.0 CY

Ask your plant what increment it batches in and what its minimum load is. NRMCA puts truck mixer capacity at 8 to 12 cubic yards and advises against small clean-up loads, so a 14 CY slab is likely two trucks. Pricing works the same way: the order quantity times your supplier's quoted rate per yard, never the neat volume.

How to estimate concrete in bags for small pours

Small pads, post footings and repairs are often bagged instead of trucked. Quikrete's Concrete Mix data sheet lists an 80 lb bag at about 0.60 cubic feet and a 60 lb bag at about 0.45 cubic feet. Those are typical yields for that product, and the label on the bag you buy wins.

The four F2 pads in the example are 36 CF. 36 ÷ 0.60 = 60 bags of 80 lb mix before any overage. At 7%, 60 × 1.07 = 64.2, so 65 bags. One cubic yard at that yield is 27 ÷ 0.60 = 45 bags, which is why most crews stop bagging once the pour gets past a yard or two.

Common concrete takeoff mistakes

Foundations often carry block or brick on top, and that work is measured in square feet of wall, not cubic yards. The masonry takeoff guide picks up from there.

Doing a concrete takeoff from a PDF

Most of the time on a concrete takeoff goes into the measuring: centerline runs, slab areas, and checking the scale before you trust any of it. The architectural scale on each sheet is what turns a PDF into feet.

In MeasureFloorPlan you upload the PDF set, set the scale by clicking both ends of one dimensioned wall, then click runs with the Distance tool for linear feet of footing and trace slabs, walks and drives for area. Enter the thickness and it gives cubic yards to order. Runs can be grouped into named line items with subtotals (F1 footing, stem wall), and the quantities export to Excel (CSV) or PDF. See concrete takeoff software for the details. There is a free demo on a sample plan; Starter is $9 a month for 3 plans and Pro is $29 a month unlimited.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

Frequently Asked Questions

What is the concrete takeoff formula?

Cubic yards = length (ft) × width (ft) × thickness (ft) ÷ 27. If the thickness is in inches, divide by 324 instead of 27, because 27 × 12 = 324. Run it once for every footing, wall, slab and pad, then add the lines up.

How do you estimate a concrete slab in cubic yards?

Multiply the slab area in square feet by the thickness in feet and divide by 27. A 1,000 SF slab at 4 inches is 1,000 × 0.3333 = 333.3 cubic feet, and 333.3 ÷ 27 = 12.35 cubic yards before overage. Thickened edges and footings under the slab go on their own lines.

How much extra concrete should you order?

The National Ready Mixed Concrete Association says to order 4% to 10% more than the volume calculated from the plan dimensions, to cover contingencies. Use the low end on a well-formed slab and more on rough trenched footings, and apply it to each pour separately.

How do you convert concrete cubic yards to tons?

Multiply cubic yards by 27 to get cubic feet, then by the unit weight. Quikrete lists its bagged Concrete Mix at about 140 lb per cubic foot, so one cubic yard of that product is 27 × 140 = 3,780 lb, about 1.9 tons. Your supplier can give the unit weight of its own mix.

How many 80 lb bags of concrete make a cubic yard?

Quikrete rates an 80 lb bag of its Concrete Mix at about 0.60 cubic feet. A cubic yard is 27 cubic feet, so 27 ÷ 0.60 = 45 bags, before any waste. Check the yield printed on the bag you are buying.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.