Landscape Takeoff: How to Measure Sod, Beds, Plants and Hardscape From Plans

A landscape takeoff measures the site and planting plans for everything you will price: lawn areas in square feet, planting beds in square feet, mulch and soil in cubic yards, plants counted by size, edging in linear feet, and hardscape by area and base volume. Measure each area once, then convert it into what you order: sod pallets, yards of mulch, flats or pots of plants and tons or yards of base.
Measure Plans in Minutes
Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.
A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.
What do you measure in a landscape takeoff?
Most lines start as an area, a length or a count. The conversion to an order quantity comes after, and it is where most of the money gets lost.
| Item | Measured as | Ordered as |
|---|---|---|
| Sod | SF of lawn area | Slabs or rolls, then pallets |
| Seed | SF of lawn area | Pounds, at the rate on the seed label or spec |
| Mulch | SF of bed area x depth | Cubic yards (CY) or bags |
| Topsoil or planting mix | SF x depth | CY |
| Trees and shrubs | Count by symbol | EA, by size (caliper, gallon) |
| Groundcover and mass planting | SF of bed x spacing | EA, then flats or pots |
| Bed edging | LF along the bed line | Pieces at your supplier's length |
| Pavers and patios | SF of surface | SF of pavers plus base CY and edge restraint LF |
Irrigation is usually its own takeoff, with pipe by size in LF and heads, valves and controllers counted in EA. The units are explained in more detail in construction units of measure.
Which sheets hold the landscape quantities?
The planting plan (often an L sheet) shows beds, lawn and every plant as a symbol. The plant schedule on the same sheet lists each plant with its common and scientific name, quantity, container size and spacing. A hardscape or layout plan carries patios, walks and edging, and the details show base depths and edge restraints.
The UF/IFAS guide to drawing a planting plan describes the schedule as a list of all plants with the total quantity of each, used for pricing and installation, and notes that planting plans are typically drawn at 1 inch = 10 feet. That is an engineer's scale, not an architect's, so read the scale note before you measure; the difference is covered in how to read an architectural scale.
Treat the schedule quantity as the designer's number, not yours. Count the symbols yourself and compare. If they disagree, send a question to the designer before you bid.
Sod takeoff: how to get from square feet to pallets
Measure each lawn area in square feet, subtract anything inside it that is not lawn (beds, walks, pads), and add your waste. Then convert to pieces and pallets. A 16 x 24 inch slab is 16 x 24 = 384 square inches, and 384 / 144 = 2.667 SF.
Pallet size varies by farm. University of Tennessee Extension says a pallet of slab sod usually holds about 50 square yards (50 x 9 = 450 SF), that slabs are often 16 inches wide by 24 or more inches long, and that big-roll sod comes in rolls 24, 30 or 48 inches wide and up to 100 feet long. Those are typical figures. Your supplier's pallet count is the one to use.
How to calculate mulch and topsoil in cubic yards
A cubic yard is 27 cubic feet. Spread 1 inch deep, that covers 27 x 12 = 324 SF, which matches the Clemson Extension mulch factsheet. So the formula for any bed is CY = SF x depth in inches / 324.
Take the depth from the planting notes or spec. Clemson's typical guidance is no more than 2 to 3 inches for fine wood and bark mulch and up to 4 inches for coarse pine bark nuggets. The same formula works for topsoil, planting mix and paver base, using the depth on the plan or detail. For odd shapes, the cubic footage calculator does the volume math.
How do you count plants from a planting plan?
Trees and specimen shrubs are drawn one symbol per plant, so you count them by type, one symbol at a time, the same way as the method in the count takeoff guide. Mass plantings and groundcover are drawn as a hatched bed with a spacing, so you measure the bed and calculate the count.
On a square grid, plants per square foot = 144 / spacing in inches squared. At 12 inches o.c. that is 144 / 144 = 1 plant per SF. The University of Illinois Extension groundcover chart gives the same figures per 100 SF: 400 at 6 inches, 225 at 8 inches, 100 at 12 inches and 45 at 18 inches. It also recommends a staggered or diamond pattern.
Staggered spacing packs more plants into the same bed. Each plant still sits 12 inches from its neighbors, but the rows close up to 12 x 0.866 = 10.4 inches apart (0.866 is the height of an equilateral triangle with sides of 1). That gives 1 / 0.866 = 1.155 plants per SF at 12 inches, about 15.5% more than the square grid. Check the plan notes for which pattern the designer used.
Landscape takeoff example: a commercial frontage
Say the planting plan for a small office building shows two lawn areas, a set of mulched beds with a groundcover bed inside them, trees and shrubs by symbol, steel edging along the lawn line and a paver patio. The depths and allowances below are example values from an imagined spec, there to show the math.
| Line | Measured | Math | Order |
|---|---|---|---|
| Sod | 2,400 + 1,150 = 3,550 SF | 3,550 x 1.05 = 3,727.5 SF | 1,398 slabs, 9 pallets |
| Mulch at 3 in | 1,280 SF of beds | 1,280 x 3 / 324 = 11.85 | 12 CY |
| Topsoil under sod at 4 in | 3,550 SF | 3,550 x 4 / 324 = 43.83 | 44 CY |
| Groundcover, 12 in o.c. staggered | 420 SF bed | 420 x 1.155 = 485.1 | 486 EA |
| Trees and shrubs | Counted by symbol | Checked against schedule | By size, EA |
| Steel edging | 236 LF | Measured along the lawn line | 236 LF |
| Paver patio | 18 x 24 = 432 SF | Base at 6 in: 432 x 6 / 324 = 8 | 432 SF, 8 CY base |
| Patio edge restraint | 18 + 24 + 18 = 60 LF | Building side excluded | 60 LF |
Sod, step by step: 2,400 + 1,150 = 3,550 SF of lawn. At an example 5% allowance, 3,550 x 1.05 = 3,727.5 SF. In 16 x 24 slabs, 3,727.5 / 2.667 = 1,397.6, so 1,398 slabs. At 450 SF per pallet, 3,727.5 / 450 = 8.28, which rounds up to 9 pallets. If your farm sells whole pallets only, the leftover on the ninth pallet is part of the price.
Mulch: 1,280 x 3 = 3,840, and 3,840 / 324 = 11.85, so 12 CY. The 420 SF groundcover bed sits inside those 1,280 SF and gets mulched too. Groundcover: 420 x 1.155 = 485.1, so 486 plants; on a square grid it would be 420 x 1 = 420. That 66-plant gap is why the pattern note matters.
Patio: 18 x 24 = 432 SF of pavers. A 6 inch base is 0.5 ft, so 432 x 0.5 = 216 cubic feet, and 216 / 27 = 8 CY. The patio perimeter is 18 + 24 + 18 + 24 = 84 LF, but the 24 ft side runs along the building, so edge restraint is 84 minus 24 = 60 LF. Add your own waste to the pavers using construction waste factors and your cut pattern.
Common landscape takeoff mistakes
- Measuring the whole lot as lawn and forgetting to subtract beds, walks and pads.
- Reading a 1 inch = 10 feet sheet with an architect's scale.
- Pricing the schedule quantity without counting the symbols on the plan.
- Counting groundcover on a square grid when the notes call for staggered spacing.
- Mixing square feet and square yards, or forgetting to divide by 27 for cubic yards.
- Ordering partial pallets that the farm will not sell.
Building trades hit the same traps. A painter pricing the building next to your frontage works from areas the same way, as in the painting estimate guide, and a mechanical sub on the same job measures duct by length and size, shown in the HVAC duct takeoff guide.
How to do a landscape takeoff on a PDF
When the plans come as a PDF site plan or survey, you set the scale from a printed dimension or the scale bar, then trace lawns and beds for area, click along bed lines for edging, and count plant symbols.
In MeasureFloorPlan, a site plan or survey works the same as a floor plan as long as it is drawn to scale and has one printed dimension, and each sheet of a PDF set keeps its own scale. Trace an area for square feet, use the Distance tool for linear feet, and group runs into named line items with subtotals. In Takeoff mode the Count tool (keyboard shortcut C) takes one click per plant, and the Other category takes a custom name such as 5 gal shrub. Quantities export to CSV, Copy table and PDF, so your sod, mulch and plant math can run in your own sheet.
It is built for measuring, not a full landscape estimating suite; see landscape estimating software for what it covers. There is a free demo on a sample plan; Starter is $9 a month for 3 plans and Pro is $29 a month unlimited, with a 48-hour money-back guarantee.
Measure Plans in Minutes
Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.
A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.
Frequently Asked Questions
What is a landscape takeoff?
It is the list of quantities a landscape contractor prices from the plans: sod and seed in square feet, mulch and soil in cubic yards, plants counted by size, edging in linear feet, and hardscape such as pavers and base. Each line carries the sheet it came from and its unit.
How do you estimate sod needed for a job?
Measure every lawn area on the site plan in square feet and subtract beds, walks and patios inside it. Add your waste allowance, divide by the square feet per slab or roll to get pieces, and divide by the square feet per pallet from your supplier to get pallets, rounding up each time.
How many square feet are on a pallet of sod?
It depends on the farm. University of Tennessee Extension says a pallet of slab sod usually holds about 50 square yards, which is 450 square feet, and slabs are often 16 inches wide by 24 or more inches long. Ask your supplier for the exact pallet coverage before you order.
How much area does a cubic yard of mulch cover?
Clemson Extension puts it at 324 square feet at 1 inch deep. Divide 324 by your depth in inches for other depths: 162 square feet at 2 inches and 108 square feet at 3 inches. For a bed, cubic yards = square feet x depth in inches / 324.
What does o.c. mean on a planting plan?
On center: the distance from the center of one plant to the center of the next at planting. The plant schedule gives it for shrubs and groundcover, and you use it with the bed area to count plants. At 12 inches o.c. on a square grid, 100 square feet takes 100 plants.