Construction Plan Sets: What Each Sheet Is For

Construction Plan Sets: What Each Sheet Is For

A construction plan set is the full package of drawings for a project, grouped by discipline and listed in a sheet index on the cover sheet. General sheets come first, then civil, structural, architectural and the trade sheets, each numbered so you can tell what it is from the number alone. Knowing that order is how you find your scope fast and spot a missing sheet before it costs you on a bid.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

What is in a construction plan set?

Every plan set has general sheets (cover, sheet index, notes, symbols and abbreviations) and then one group of sheets per design discipline. Within each group you get plans, then elevations, sections, enlarged views, details and schedules.

The drawings are only half of what you bid from. The written specifications come with them and describe the products and how they go in. If you are new to the drawings themselves, start with how to read blueprints for construction.

What order do the sheets in a plan set go in?

Most U.S. sets follow the Uniform Drawing System in the U.S. National CAD Standard. It assigns each discipline a letter, and sets are normally arranged in the order the standard lists them. A typical commercial set runs G, C, L, S, A, I, then F, P, M, E and T.

LetterDisciplineLetterDisciplineLetterDiscipline
GGeneralHHazardous MaterialsVSurvey/Mapping
BGeotechnicalCCivilLLandscape
SStructuralAArchitecturalIInteriors
QEquipmentFFire ProtectionPPlumbing
DProcessMMechanicalEElectrical
WDistributed EnergyTTelecommunicationsRResource
XOther DisciplinesZContractor/Shop DrawingsOOperations

Read the table left to right, top to bottom, for the set order. Few projects use all 21, and small jobs simply skip the letters they do not need.

Complex jobs can use a second letter to split a discipline further. The standard's example is ET for telecommunications drawn by the electrical engineer. With a two-letter designator, the hyphen is dropped.

How does construction sheet numbering work?

A sheet number has three parts: the discipline letter and a hyphen, one digit for the sheet type, and a two-digit sequence number. A-101 is the first architectural plan sheet.

A-101Discipline: A-ArchitecturalSheet type: 1PlansSequence: 01First sheet of its type

The sheet type digit is the part worth memorizing, because it works the same way in every discipline.

DigitSheet type
0General: symbols legend, notes
1Plans
2Elevations
3Sections, including wall sections
4Large-scale views: enlarged plans, elevations, stair sections
5Details
6Schedules and diagrams
7User defined, including typical detail sheets
8User defined
93D views: isometrics, perspectives, photos

Sequence numbers start at 01, and 00 is not used. They do not have to run without gaps, so the designer can slot a sheet in later. Some offices also match the floor across disciplines, so A-102, M-102 and E-102 are all second-floor plans. Not every office follows the standard to the letter, so let the sheet index settle any doubt.

What is on the cover sheet and sheet index?

The cover or title sheet carries the project title, the owner, the consultants, building code information and the index of drawings. A sheet index for a small two-story building might look like this.

SheetTitle
G-001Cover Sheet and Sheet Index
C-101Site Plan
S-101Foundation Plan
S-102Roof Framing Plan
A-001General Notes, Symbols and Abbreviations
A-101First Floor Plan
A-102Second Floor Plan
A-201Exterior Elevations
A-301Building Sections
A-501Details
A-601Door and Window Schedules
P-101Plumbing Plan
M-101Mechanical Plan
E-101Power Plan
E-102Lighting Plan

The general notes and abbreviations on A-001 apply to every architectural sheet after it. The short forms used there are covered in construction abbreviations on blueprints.

Permit set vs bid set vs construction set vs as-builts

The same project goes through several issues of drawings, and the stamp or issue date on the title block tells you which one you are holding. Price from the wrong issue and you are pricing a different building.

SetWhat it isWho issues it
Estimate setDrawings stamped "For Estimate Only"Design team
Bid setThe drawings and specs contractors price from; changes during bidding come as addendaDesign team
Permit setDrawings submitted for the building permit; may match the bid set or differDesign team
Construction set (CDs)Drawings issued at the completion of design, for buildingDesign team
As-built drawingsField markups showing actual locations and changesContractor
Record drawingsClean final set compiled from the originals, site changes and the as-builtsArchitect, when contracted

These definitions follow Cornell's drawing type definitions and a joint architect and contractor statement on as-built and record drawings. Many owners also issue a conformed set after bidding, with the addenda folded into the drawings. Usage varies, so read the contract to see which set governs.

Which sheets does each trade need for a takeoff?

No trade can bid from its own sheets alone. Heights live in sections, finishes live in schedules, and some scope only shows up in a general note. This is a typical starting list. Your set may put things elsewhere.

TradeMain sheetsAlso check
FlooringA plans (1-series)Finish schedule, transition details
DrywallA plans, wall type legendSections for heights, ceiling plan, details
PaintingFinish schedule, A plansElevations, ceiling plan, door schedule
Doors and hardwareDoor scheduleA plans for tag count, details
ConcreteS foundation plansS sections and details, C site plan
FramingS framing plansA sections, wall types, details
RoofingA roof planElevations, sections, roof details
PlumbingP plans and fixture scheduleA plans, riser diagrams
HVACM plans and equipment schedulesCeiling plan, sections
ElectricalE power and lighting plansPanel schedules, ceiling plan

Write the sheet number on every line of your takeoff. When an addendum reissues A-301, you can find every quantity that came from it in a minute. The takeoff checklist has the rest of the pre-bid checks.

How to check the sheet index against what you received

  1. Count the sheets in the index and the pages in the file or roll you received.
  2. Tick off each sheet number, not just the count. Two missing sheets and two extras still add up.
  3. Check the issue date and latest revision on each title block against the index.
  4. List every addendum and the sheets it adds, replaces or voids.
  5. Ask for anything missing before you measure, not after.

Say the index above lists 15 sheets and the PDF has 14 pages. Ticking them off shows E-102, the lighting plan, is missing. For an electrician, that is the sheet with every fixture to count. Then Addendum 1 replaces A-102. You now need to measure the second floor from the new A-102, not the one in the original file.

Before you measure, check that each sheet printed at its stated scale. The method is in how to read an architectural scale, and the steps for measuring on screen are in how to do a takeoff from a PDF.

Measuring a whole plan set as one job

In MeasureFloorPlan, every sheet of a multi-page PDF set is part of one plan, and each sheet keeps its own scale. You set the scale from one printed dimension on a sheet, then click runs for linear feet, trace areas and count fixtures. The quantities export to Excel (CSV) or PDF. It is built for PDF plan takeoff on sets like the one above.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.

Frequently Asked Questions

What is a plan set in construction?

A plan set is the full package of drawings for one project, grouped by discipline: general, civil, structural, architectural, plumbing, mechanical, electrical and so on. It is issued together with the written specifications, and contractors bid and build from both.

What is a sheet index?

A sheet index is the list of every sheet in the set by number and title, usually printed on the cover sheet. Use it to confirm you have the whole set before you start a takeoff.

What is the difference between a permit set and a construction set?

A permit set is the group of drawings submitted to get a building permit. A construction set is issued when design is complete, for building from. On some projects they are the same drawings and on others they differ, so check the issue date and stamp on each sheet.

What is the difference between as-built and record drawings?

As-built drawings are marked up by the contractor during construction to show actual locations and changes. Record drawings are a clean set the architect compiles at the end from the original drawings, known site changes and the contractor as-builts.

Why do sheet numbers skip, like A-101 then A-104?

The National CAD Standard allows gaps in sequence numbers so sheets can be added later without renumbering the set. It also never uses 00, so there is no A-100. A gap is normal, but check the sheet index to confirm nothing is actually missing.

Measure Plans in Minutes

Upload your full plan set. Get every length, area and count. Export the takeoff to Excel.

A floor plan drawing, not a photo of a room.
Plans from $9 a month. 100% money-back guarantee.